Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74313 REL 75: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Project Number:
Title:
John Day Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
74313 REL 75
Contract Title:
1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
74313 REL 51: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
  • 74313 REL 95: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
Contractual Obligations:
Under this contract fencing projects will be completed with three private landowners and within four USFS grazing allotments on Orange, Dans, Grub, and Junkens Creeks. Approximately 12.4 miles of riparian protection fence will be constructed to protect 200 riparian acres and 8.8 miles of stream. The riparian fences will include approximately 40 gates and 7 watergaps at the sites identified below:
• WE F - Build 1.00 miles of riparian fence along the South side of Wind Creek (North side built in the 2019 work period), a tributary of the South Fork John Day River (Private property).
• WE G - Build 3.10 miles of riparian fence along Starveout Creek a tributary of the North Fork John Day River. (Private property)
• WE H - Build 1.30 miles riparian fence along the Fox Creek (Private property).
• WE I-L - Build 7 Miles of riparian fence along Orange, Dans, Grub, and Junkens and Desolation Creeks on USFS property.
• WE M - Complete a Cooperative Agreement along Neal Creek to protect 0.94 miles of stream.

Under this contract floodplain restoration projects will be designed and implemented
• WE N - Complete designs on Murderers Creek's instream structures and floodplain reconnection project with BOR on ODFW property.
• WE O - Acquire LWD for Murders Creek 2021 implementation
• WE P-Q - Complete additional designs and install 10 additional BDA's on Hay Creek (Private property).
• WE R-T - Harvest LWD and implement Tex Creek floodplain reconnection project.
• WE U - Mac Creek planting.

Background:
This project was initiated on July 1, 1984 and allows for initial landowner contacts, agreement development, project design, budgeting, and implementation for anadromous fish habitat improvement on privately owned lands within the John Day Basin. The purpose of the John Day Fish Habitat Enhancement Program is to enhance production of indigenous wild stocks of spring chinook and summer steelhead within the subbasin through habitat protection, enhancement, and fish passage improvements. The project has historically accomplished enhancement through the development of riparian enclosures and in more recent years has moved to also incorporate floodplain restoration projects into protected riparian areas to further enhance restorative processes. The Fish Habitat Program coordinates with many different agencies. The projects in Gilliam county partner with Gilliam Soil and Water Conservation District, projects in Wheeler are associated with Wheeler Soil and Water Conservation District, and the John Day Fish Habitat Program also works with the Tribal entities of both Umatilla and Warm Springs Tribes.

Project Prioritization:
The John Day Fish Habitat Enhancement Program is continually keeping in mind the prioritization of upcoming projects.  Prioritization efforts have include: using the Atlas framework which is still under development in the John Day Basin to identify priority areas and projects; working closely with the District Fish Biologist to obtain guidance when selecting projects; and working to adjoin projects in focus areas to create large contiguous habitat protections.

To facilitate reduced maintenance the John Day Fish Habitat Program has begun using steel pipe instead of wooden posts. Utilizing steel should cut down the maintenance costs significantly over the 15 year Cooperative Agreement with private landowners, which states that ODFW Fish Habitat Program will maintain for the term of the agreement.

Riparian Protection Fence Development:
The initial Riparian Fence Cooperative Agreements are for a term of 15 years and are intended to give the riparian vegetation time to get established and stable in the event that domestic livestock is allowed back into the riparian areas. During this initial agreement period ODFW commits to maintaining the riparian fence and in some cases off site cattle watering facilities as described below. From observations landowners have kept up the maintenance on the original riparian fences on approximately 90% of the expired Cooperative Agreements.  In high priority areas the program has renewed/rebuilt and/or maintained riparian protection fences for an additional 10 years.  The riparian buffer widths vary, but the averaged minimum is approximately 30 feet above the ordinary high water line. The Fish Habitat Program goals are to improve as much riparian vegetation in the 15 year Cooperative Agreement that is signed by each landowner.  The restoration of vegetation typically results in the restoration of natural stream processes and other factors such as bank/channel stability, temperature, macro/micro invertebrates, sediment transportation, magnitude of water runoff, water quality, and fisheries health.

Considerable time is spent coordinating with landowners on the Cooperative Agreement, fence alignment, gates, and water gap locations. Fish habitat staff stake structure locations and GPS the locations prior to landowner approval. The GPS coordinates are then given to Grant Soil and Water Conservation District (GSWCD) to map the riparian fence layout. GSWCD advertises the opportunity to bid on the project in the local newspaper, set up the bid packets, and determine whether each contractor is qualified and has the proper licensing, bonding and insurance requirements for the project. Cultural surveys are arranged with BPA environmental compliance personnel. A pre-bid tour of the project area is given to the contractors so they can view the terrain, fence layout, and design including all structures. Sealed bids are submitted to GSWCD by interested contractors by the due date specified on the bid packet and the project is then awarded to the lowest qualified bidder. The project time frame is established depending on the length of the project, (typically we allow 3 weeks for each mile of fence to be constructed). ODFW fish habitat personnel oversee the progress and quality of the work. In some cases materials will also be delivered by ODFW personnel to save on contractor time/money and for program efficiency. At the end of the project the Fish Habitat personnel will complete a final walk through of the project and problem areas will be flagged and corrected by the contractor before final payment is requested and paid by GSWCD through a sub contract. Because the fish habitat program has to maintain the project for 15 years, the specifications to the riparian fence construction are closely monitored. Photopoints are established at the beginning of each project and then retaken every three years.

Riparian Protection Fence Maintenance:
The John Day Fish Habitat Enhancement Program maintains new riparian projects for the term of 15 years. Currently there are approximately 213.03 miles of riparian fence associated with 53 different landowners in 11 different counties,  Gilliam, Grant, Wheeler, Crook, Harney, Jefferson, Morrow, Sherman, Umatilla, Union, and Wasco. For example, We currently have 9 projects in Gilliam county that we maintain from our main headquarters in John Day, Oregon. Just to get from John Day to Condon takes approximately three hours, then to get to half of the project sites is another hour. On these days it takes two maybe three program personnel, and ATV's to cover as much ground as possible to get a single project area maintained and put back into workable order. These are usually long days depending on wildlife, Spring run-off damage and numbers of trees that have fallen during wind storms or fire damaged areas during the summer months. There are typically trees/rocks that have fallen on project fences and structures that need fixing. In the summer months there are occasionally flash floods that go through an area which requires attention to the watergaps and mainline fences as well. Program personnel have learned to cover more ground by dropping one person off and have them walk through sections that are only accessible by foot and then drive down a mile or so leave the ATV and leap frog to the lower end. This saves time so personnel can work in one direction and not have to back track. The program keeps track of where each day maintenance has been completed and if additional materials is need on the next visit it is written down. The program has two full time positions, one 6 month (half 6 months fish Habitat and half 6 months Screens and Passage), one 5 month permanent seasonal position, and a 4 month secretarial position.

The John Day Fish Habitat Program also contracts the Grant County Weed Department. Fish habitat personnel when on riparian project sites keep an eye out for noxious weeds on the counties top ten weed list. A small budget has been set aside to spray approximately 70 acres on projects currently under cooperative agreements. This has been a great benefit to our program to be able to spray weeds within the riparian area, if nothing else to show landowners that weeds can be maintained even in high dispersal areas.

Floodplain Enhancement:
In recent years the John Day Fish Habitat Enhancement Program has began incorporating floodplain restoration components into the fencing program to enhance areas that have already had a riparian fence installed.  Currently the John Day Fish Habitat Program is working on three instream projects within the John Day Basin.

One project on Hay Creek slated in 2020 is in Gilliam County it is a continuation of work completed in the 2019 work period.  In 2019 10 BDA's where installed.  In 2020 work period 10 more will be installed within the same foot print as the original 10.  Some adaptive management may be needed after the Spring of 2020 develops.

A second project is on the Mainstem of Murderers Creek.  This project has been in the works for many years with BOR, District Fish personnel, BPA, permitting and cultural entities.  Cultural significances within this area is high.  Cultural clearance should be completed by 2020 and the LWD will be subsequently harvested under this contract and installation of the instream structures should be constructed in 2021.

Third project is on Tex Creek ODFW property.  A riparian fence was constructed in 2016 on Tex Creek. A floodplain connection design was completed in 2019 and the project will be funded by the OWEB FIP under an application submitted by the South Fork Watershed Council.
Account Type(s):
Expense
Contract Start Date:
03/01/2020
Contract End Date:
02/28/2021
Current Contract Value:
$513,721
Expenditures:
$513,721

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Program Management A: 119. Program Management 02/28/2021 02/28/2021
EC for the Fish Habitat Program B: 165. Environmental Compliance 09/28/2020 09/28/2020
Select Project Sites C: 114. Select Project Sites 02/28/2021 02/28/2021
Maintenance of Riparian Projects D: 186. Maintain Riparian Fence 02/28/2021 02/28/2021
Herbicide Application E: 198. Herbicide Application 12/31/2020 12/30/2020
Riparian Fence Installation F: 40. Phillips Property - Wind Creek 10/01/2020 06/30/2020
Riparian Fence Installation G: 40. Ecotrust Property - Starveout Creek 11/30/2020 09/30/2020
Riparian Fence Installation H: 40. Humphrey Property - Fox Creek 02/28/2021 02/28/2021
Riparian Fence Installation I: 40. USFS Property - Orange Creek 11/01/2020 09/30/2020
Riparian Fence Installation J: 40. USFS Property - Dans Creek 11/01/2020 11/01/2020
Riparian Fence Installation K: 40. USFS Property - Grub Creek 02/28/2021
Riparian Fence Installation L: 40. USFS Property - Junkens Creek 11/01/2020 09/30/2020
15 Year Cooperative Agreement on Neal Property - Long Creek M: 92. Neal Property - Long Creek 11/30/2020 11/30/2020
Murderers Creek Designs Produced N: 175. Murderers Creek Designs 02/28/2021
Juniper removal for Instream project on Murderers Creek O: 29. Murderers Creek LWD Acquisition 12/31/2020
BDA designs for Hay Creek P: 175. Hay Creek BDA Designs 07/15/2020 07/01/2020
Ten BDA's installed Q: 29. Hay Creek BDA Installation 10/01/2020 09/30/2020
Mac Creek Planted R: 47. Mac Creek - Plant Vegetation 11/30/2020 11/18/2020
Completed Annual Report T: 132. Submit Progress Report for the Period (March 1, 2019) to (February 28, 2020) 10/31/2020 09/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 7 instances of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 40 Install Fence

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Program Management
B 165 Environmental Compliance
C 114 Select Project Sites
D 186 Maintain Riparian Fence 05/28/2020
E 198 Herbicide Application 05/28/2020
F 40 Phillips Property - Wind Creek 05/28/2020
G 40 Ecotrust Property - Starveout Creek 07/01/2020
H 40 Humphrey Property - Fox Creek 01/06/2021
I 40 USFS Property - Orange Creek 07/01/2020
J 40 USFS Property - Dans Creek 07/01/2020
K 40 USFS Property - Grub Creek 07/01/2020
L 40 USFS Property - Junkens Creek 05/28/2020
M 92 Neal Property - Long Creek 05/28/2020
N 175 Murderers Creek Designs 07/07/2020
O 29 Murderers Creek LWD Acquisition
P 175 Hay Creek BDA Designs 05/28/2020
Q 29 Hay Creek BDA Installation 05/28/2020
R 47 Mac Creek - Plant Vegetation 05/28/2020
S 185 Periodic Status Reports for BPA
T 132 Submit Progress Report for the Period (March 1, 2019) to (February 28, 2020)